On October 20, part of Google Cloud's London region went dark for about six hours, and the backup generators never started. Google's final report, covered by The Register, is worth reading for anyone who owns failover testing, even if you never touch a power plant. The backup was there. The logic deciding when to use the backup was looking at the wrong thing.
The facility runs on two independent utility feeds plus a bank of generators. After a quarterly generator load test on October 14 turned up problems, the team opened the breaker on feed B for repairs, leaving feed A to carry the whole load. Then an underground cable outside the site failed and took feed A down. According to the breakdown of the report, the controller sensed voltage upstream of feed B's open breaker. The line there was still live, so both redundant controllers, running identical logic, saw a healthy source and never sent the generators a start signal. The UPS batteries, sized for about five minutes, ran out during a manual transfer.
Failover testing in the reduced state
Two things went wrong together, and neither was exotic. The system was in a maintenance posture, running on one feed instead of two. And the health check measured a point near the power, not the power the load was getting. The redundant controller didn't help, because a second copy of the same logic makes the same mistake.
Software teams build the same trap all the time. A health check pings a load balancer instead of running a real query. A replica gets promoted only if a monitor says the primary is down, and the monitor lives on the primary. A cluster loses one node for an upgrade, and nobody has ever tested what happens when a second node fails that same afternoon. Maintenance is often where the trouble starts. Microsoft said an automated maintenance process in Azure Storage stopped part of its Brazil South storage from processing requests on November 4, and the same issue came back the next morning, as one affected vendor wrote in its public incident report.
Our view is simple. Run your failover drills while something is already degraded, because that's when real failures like to arrive. For each automatic switch, write down what signal triggers it and where that signal is measured, then ask whether it would still read true if the thing it watches were half broken. When you take a component out for maintenance, treat that window as a period of lower protection, with a named person watching and a manual fallback you've rehearsed.
Google says it has reprogrammed the controllers and run a generator transfer test under full load. Which of your own backups has only been tested on a good day?